We have collected the amount of pesos $932,200 for this concept which corresponds to 45% of the total. We have started the painting of the buildings with a 60% advance on this job, also, we have started the tubing of the building for the air conditionings water collection with an advance of 40%. Making of the trays will start by mid July.
Depending on how fast we can collect the balance amount of the assessment, we expect to start the remaining maintenance projects as follows:
![]() |
Project |
Date |
Transformers |
August `07 |
Emergency plant |
|
Boiler |
August `07 |
Swimming pool tubing |
September `07 |
Hot water tank |
October ‘07 |